One Land Rig. Thousands of Details. One Controlled Move Basis.

“Move the land rig” is not an executable scope. A credible program identifies the commercial and operating parties, equipment boundary, current configuration, move state, origin and destination, responsibilities, technical releases, transport sequence, customs treatment, required-on-site date, destination readiness, and final disposition before price or schedule is treated as firm. This service applies to land and onshore drilling rigs—not intact offshore rigs or MODUs.

OGL converts those inputs into a controlled logistics work package and personally drives the interfaces from preliminary planning through mobilization, demobilization, redeployment, return, storage, or repair.

CONTROL REFERENCE
OGL-RS-01

RIG LOGISTICS CONTROL

Land-rig moves and offshore parts under one visible control record.

Asset

REGISTER

Release

GATE

Route

CONTROL

Close

RECONCILE

▪

FMC-Licensed Ocean Freight Forwarder

▪

OGL License No. 023947F

▪

NVOCC Services Through OnBoard Global Logistics LLC

▪

OnBoard License No. 027470N

▪

Houston Hub • Qualified Global Alliance Network

OGL · RIG SOLUTIONS
ONSITE GLOBAL LOGISTICS · CONTROLLED INTERFACE RECORD
DOCUMENT OWNER
OGL PROJECT DESK
Basis-of-Move Lifecycle OGL-RS-01

The land-rig move is only complete when the asset record closes.

A complete land-rig move is a linked release system. Each phase inherits approved data, open actions, custody, customs status, and technical decisions from the phase before it—then produces evidence for the next gate. This lifecycle does not describe movement of an intact offshore rig.

01

Define Basis

Rig, contract, countries, asset boundary and responsibility map

02

Release Equipment

Identity, condition, technical release and readiness evidence

03

Mobilize

Origin sequence, providers, staging, bookings and custody

04

Cross Border

Export, transport, import and controlled exceptions

05

Deliver & Receipt

Destination sequence, handoff and discrepancy control

06

Reconcile & Close

Returns, temporary entry, substitutions and final dossier

OGL controls the connecting logistics record. Rig configuration, engineering, technical release, lift approval, operating procedures and technical acceptance remain with the contractually appointed qualified parties.
01

Licensing & Execution Confidence

  1. Contract-to-Cargo Responsibility Mapping
  2. Heavy-Haul + Port + Ocean Coordination
  3. Return + Redeployment + Closeout
  1. Serial-Level Asset and Customs Control
  2. Destination Sequence + Final Handover
02

The Basis of Move Comes Before the Booking.

A drilling contract, rental agreement, equipment schedule, operator procedure, rig owner requirement, customs regime, carrier contract, and destination plan can assign different responsibilities to different parties. OGL establishes what is included, excluded, supplied, approved, reimbursable, standby-sensitive, owner-furnished, contractor-furnished, temporary, consumable, replaceable, returnable, or subject to a condition requirement.

The result is a move basis that senior stakeholders can review before transport commitments create exposure.

03

Complete Land-Rig Move Lifecycle

Phase OGL Logistics Focus Controlled Outputs
Opportunity and tender Rig and country profile, preliminary asset boundary, route and mode concepts, provider market, commercial assumptions, schedule exposure Basis-of-move draft, clarification register, ROM logistics input, responsibility assumptions
Award and mobilization planning Contract review, owner/operator/drilling-contractor interfaces, data requirements, HSE and quality requirements, provider qualification, reporting Execution plan, responsibility matrix, communication plan, provider matrix, master action register
Asset and release preparation Equipment identity, dimensions, weights, centers of gravity where required, condition, isolation, packing, preservation, DG and controlled-item status Asset register, package register, readiness forecast, document register, hold-point log
Origin execution Rig-down logistics interface, cranes and rigging handoff, heavy-haul sequence, staging, route and permits, port or airport delivery Origin sequence, dispatch register, custody record, permit and booking status, daily report
International movement Ocean, air, charter, breakbulk or multimodal execution; terminal, vessel, customs, export, tracking and exceptions Shipment files, movement status, customs and authorization register, exception actions
Destination execution Import release, storage or staging, heavy haul, escorts, access, delivery sequence, receiving readiness, handover Destination plan, delivery and staging sequence, proof of receipt, discrepancy register
Demobilization or onward move Condition and disposition, repair, storage, sale, return, new destination, provider and customs reassessment Demobilization basis, onward-move plan, updated asset and customs register
Closeout Temporary-entry discharge, re-export, carnet or bond evidence, returns, repairs, consumptions, substitutions, damage and open items Reconciliation statement, customs closeout, final dossier, outstanding-action register
04

The Rig Equipment Boundary Must Be Explicit.

The controlled equipment boundary can include the mast or derrick, substructure, drawworks, top drive, rotary equipment, mud pumps, mud systems, tanks, engines, generators, SCR or VFD houses, control cabins, pipe-handling systems, BOP and well-control equipment, compressors, catwalks, cranes, camps, workshops, vehicles, tubular-handling equipment, fuel and water systems, tools, testing equipment, consumables, chemicals, spares, loose gear, rental items, owner-furnished equipment, third-party service equipment, and return cores.

Not every item follows the same commercial, technical, customs, hazardous-materials, preservation, ownership, or return logic. OGL uses line-item status so “complete land rig” never becomes a blanket description that hides unresolved exceptions.

04

Comprehensive Project Logistics Scope

Project Planning & Controls

01

We establish clear communication protocols, reporting structures, and milestone tracking from the start. OGL ensures all parties understand the schedule, requirements, and escalation paths.

Origin Consolidation

02

We coordinate the collection of materials from multiple suppliers to a central hub, optimizing shipments and reducing transport costs while ensuring all components arrive together.

Crating & Export Packing

03

Through qualified packing partners, we ensure your cargo is protected for international transit, complying with all necessary regulations and standards.

Heavy Lift & Out-of-Gauge

04

We manage the specialized transport of oversized and heavy equipment, coordinating route surveys and specialized carriers.

Global Transport

03

We arrange breakbulk, ship chartering, and special air charter services through vetted alliance partners, selecting the right mode for your cargo and schedule.

Site Delivery & Final Mile

04

We coordinate the final leg of the journey, ensuring safe and timely delivery to the project site, managing local transport and unloading requirements.

05

Rented Rig and Fleet Interfaces

Question Why it matters to the move
Who owns, leases, operates, and maintains each equipment group? Establishes authority, valuation, insurance, technical release, customs party, and return condition.
What does the drilling contract identify as contractor versus operator equipment? Prevents ownership and responsibility gaps at origin, destination, and demobilization.
Which items can be consumed, substituted, cannibalized, repaired, or replaced? Protects the asset register and temporary-admission closure.
What condition, test, certificate, preservation, or inspection is required at handover and return? Defines release gates and claim evidence.
Who carries delay, standby, damage, port, storage, duty, tax, and demurrage exposure? Aligns operating decisions with the commercial contract.
06

Move Data That Drives the Plan

The initial data request covers rig type and configuration, owner and drilling contractor, current and destination locations, scope boundary, move state, equipment schedules, weights and dimensions, centers of gravity and lift data where needed, serial or asset identity, condition, ownership, values, origins, packing, preservation, DG and controlled-item status, technical releases, route constraints, facilities, cranes, transport sequence, customs history, expected duration, onward or return destination, required-on-site date, rig-up sequence, and closeout expectations.

Unknown data is not hidden. It is assigned an owner, due date, confidence level, decision impact, and hold point.

07

Responsibilities Stay Visible

OGL Coordinates Contractually Appointed Authority Produces, Approves, or Executes
Basis of move, asset data workflow, responsibility matrix, readiness and schedule controls Rig configuration, technical release, operating sequence, rig-down/rig-up procedure, commissioning and acceptance
Route, lift, packing, port, vessel and destination information workflow Engineering calculations, lift and rigging design, route engineering, certified methods, and technical acceptance
Customs and export information register, broker interface, filing and authorization status Tariff and valuation decisions, export jurisdiction and license determination, customs ruling, and government authorization
Provider and deliverable register, comments, approval status and hold points Provider execution, competent-person decisions, regulator, class, flag, owner, insurer or survey approval

Related Services

Related Capabilities

∇ Onshore Rig Moves: Land-rig heavy-haul, route, fleet, lifting, journey, and site-sequence control.

∇ Rig Spares & Repair Returns: Critical parts, RMA, repair and field-receipt control.

∇ Heavy Lift & Out-of-Gauge: Qualified technical and transport-provider coordination for oversized modules.

∇ Offshore Rig Parts & Spares Logistics: Supporting parts, supply-base handoff, field receipt, backload and repair-return control only.

∇ Mobilization Compliance: Customs, export, temporary-admission, DG and controlled-exception gates.

Decision Support

Frequently Asked Questions

Clear answers for procurement, project controls, logistics, and site teams evaluating the execution path.

 

01
Can OGL quote a complete land rig move from an equipment list?

A preliminary list can support clarification and budget development. A committed solution requires responsibility, condition, release, packing, dimension and weight, technical, route, facility, customs, export, provider, insurance, destination, sequence, and timing information appropriate to the selected modes and countries.

02
Does OGL perform rig-down and rig-up?

OGL coordinates the logistics interface around the owner’s or drilling contractor’s approved rig-down and rig-up program. Technical execution, supervision, commissioning, function testing, and acceptance remain with the appointed qualified parties unless a separately documented and insured scope establishes otherwise.

03
When is a rig move considered closed?

Physical delivery is one milestone. Commercial and regulatory closeout also requires reconciliation of the asset register, discrepancies, proof of receipt, temporary entries, re-exports, repairs, substitutions, consumptions, losses, damage, claims, and outstanding actions.